Author: Byron Bennett
Project Number:
District and General Location: North Mainland District Water Loops installation along Hautala, Bailey Road, Old Jesup Road, and Golden Isles Parkway.
Total Budget: $2.M
Anticipated Construction Completion Date: Summer 2023
Details: The project consists of water loop installations along Hautala, Bailey Road, Old Jesup Road, and Golden Isles Parkway in the North Mainland District via open-cut and trenchless methods.
Purpose: The purpose of the project is to eliminate dead...
Project Info – North Mainland – Canal Road Water Production Facility
Project Number:
District and General Location: North Mainland District Canal Road Well Site at104 Canal Road
Total Budget: $TBD
Anticipated Construction Completion Date: Summer 2023
Details: The project consists of the conversion of an existing fire well to a Water Production Facility on Canal Road in the North Mainland District.
Purpose: The purpose of the project is to meet supply-demand and capacity, water storage capacity, and increased fire flow capacity into the region.
Have More...
Project Info – North Mainland – Community Road Sewer Expansion
Project Number:
District and General Location: North Mainland District in the Community Road Business Area
Total Budget: $TBD
Anticipated Construction Completion Date: Summer 2023
Details: The project consists of 12-inch Water and 12-inch Sewer Extension rehabilitation along the Community Road Business Area in the North Mainland District.
Purpose: The purpose of the project is to provide the capacity to serve and extend critical infrastructure with new service lines. This will reduce the...
Project Info – North Mainland – Arco Water & Sewer Extension
Project Number: #2016
District and General Location: North Mainland District in the Arco Area Neighborhood
Total Budget: $4.1M
Anticipated Construction Completion Date: Winter 2022
Details: The project consists of 8-inch Water and 8 to 10-inch Sewer Extension rehabilitation along the Acro Area Neighborhood in the North Mainland District.
Purpose: The purpose of the project is to provide capacity to serve, extend critical infrastructure with new service lines, and enhance fire protection....
Project Info – Pump Station 2002 Forcemain Replacement
Project Number: #2014
District and General Location: Saint Simons Island District along Arnold Road
Total Budget: $TBD
Anticipated Construction Completion Date: TBD
Details: The project consists of 12-inch forcemain rehabilitation along Arnold Road in the Saint Simons Island District.
Purpose: The purpose of the project is to prioritize pipe repairs, rehabilitation, and replacements based on a risk-based, asset management strategy balancing the probability of a pipe failure versus the...
The Flow Show – Episode 10
What’s the latest project news at the JWSC? Check out Episode 10 of the Flow Show with Jason Vo with special guest Andy Leanza, Director of Emergency Management of Glynn County, GA.
Project Info – Mainland – Water Pollution Rehab-Academy
Project Number: #906
District and General Location: Academy Creek Water Pollution Control Plant on 2909 Newcastle Street.
Total Budget: $7.2M
Anticipated Construction Completion Date: Summer 2022
Details: The project has a variety of system improvement projects related to rehabilitation or replacement of unit processes and facilities at the plant to ensure continuous and reliable operations.
Purpose: The purpose of the project is to more effectively treat current flows and treat the...
Project Info – Mainland – Basin 4036 CIPP
Project Number: #2001
District and General Location: North Mainland District Pump Station 4036 Gravity Basin
Total Budget: $1M
Anticipated Construction Completion Date: Summer 2022
Details: The project consists of Cleaning, Closed-circuit television, and Cure-in-Place Pipe (CIPP) rehabilitation of the sewer mainline in the North Mainland District Pump Station 4036 Gravity Basin ranging from 15-inch to 30-inch in diameter
Purpose: The purpose of the CIPP process is to reduce and eliminate...
Project Info – Mainland – SPLOST 2016 Forcemain Reroute
Project Number: #702
District and General Location: North Mainland District along Harry Driggers Blvd, Canal Road, and Ogden Road
Total Budget: $4.7
Anticipated Construction Completion Date: Summer 2022
Details: The project consists of nearly 20,000 linear feet of 12- to 20-inch forcemain and 2,500 linear feet of 12 to 14-inch watermain will be installed via an open cut or trenchless directional drill method.
Purpose: The purpose of the project will reduce maintenance calls and...
Project Info – Systemwide – Annual Galvanized Replacement Program
Project Number: #2021
District and General Location: Various locations in North mainland, South Mainland, and Saint Simons Island District
Total Budget: $250k
Anticipated Construction Completion Date: TBD
Details: The project consists of an annual allotment to remove galvanized lines that have corroded from the inside out, causing pinhole leaks, rusty color water, and fluctuation in water temperature and pressure.
Purpose: The purpose of the project is to improve water quality and system...