    • Project Number:
    • District and General Location: Academy Creek Water Pollution Control Plant on 2909 Newcastle Street.
    • Total Budget: $1.5M
    • Anticipated Construction Completion Date: TBD
    • Details: The project consists of replacing existing return activated sludge (RAS) pumps, piping, and electrical with chopper-style pumps due to the existing equipment systems reaching the end of their service life and needing to be replaced.
    • Purpose: The purpose of the project is to replace aging equipment to maintain a high level of service and reliability at the wastewater treatment plant.