Today we take a look at 3 projects currently in progress here at the JWSC.
The Flow Show – Episode 17
Currently, the JWSC has around 16 active construction projects we manage. I want to report our progress on three of them: North Mainland Water Loops Construction, Pump Station 4044 Rehabilitation Project, and Dunbar Creek Water Pollution Control Facility Rehab.
For More info, please visit. www.bgjwsc.org
HWY 341/Crispen BLVD
Project Number: #2215B
District and General Location: North Mainland District HWY 341 and Crispen BLVD Intersection
Total Budget: $700k
Anticipated Construction Completion Date: November 2023
Details: The project consists of a sewer line repair that has corroded from the inside out, causing a sinkhole underneath the roadway. The anticipated start date will be following the Labor Day holiday.
Purpose: The purpose of the project is to repair the failed sewer line and restore the roadway pavement.
Have...
The Flow Show 15
Today we look at a few projects currently in process at the JWSC.
The Flow Show – Episode 13
During this episode of The Flow Show, we take a look at a few projects from the JWSC. These projects include the rehab of the Oglethorpe & Glynn Place Mall elevated storage tank, LS 2002 Forcemain installation, and a system-wide water meter replacement program.
The Flow Show – Episode 10
What’s the latest project news at the JWSC? Check out Episode 10 of the Flow Show with Jason Vo with special guest Andy Leanza, Director of Emergency Management of Glynn County, GA.
The Flow Show – Episode 9
What’s the latest project news at the JWSC? Check out Episode 9 of the Flow Show with Jason Vo!
The Flow Show – Episode 8
What’s the latest project news at the JWSC? Check out Episode 8 of the Flow Show with Jason Vo!