What’s the latest project news at the JWSC? Check out Episode 10 of the Flow Show with Jason Vo with special guest Andy Leanza, Director of Emergency Management of Glynn County, GA.
Commission Meeting Agenda – Thursday, May 19, 2022 @ 2:00 PM
For your consideration, please review the agenda for the Commission Meeting scheduled to be held on Thursday, May 19, 2022 at 2:00 p.m. in the Commission Meeting Room.
Commission_Agenda_May_19_2022–
Finance Committee Meeting Agenda – Wednesday, May 18, 2022 @ 3:00 PM
For your consideration, please review the agenda for the Finance Committee Meeting scheduled to be held on Wednesday, May 18, 2022 at 3:00 p.m. in the Commission Meeting Room.
Finance_Agenda_May_18,_2022 – Posted 5/13/22
Facilities Committee Meeting Agenda – Wednesday, May 18, 2022 @ 1:00 PM
For your consideration, please review the agenda for the Facilities Committee Meeting scheduled to be held on Wednesday, May 18, 2022 at 1:00 p.m. in the Commission Meeting Room.
Facilities_Agenda_May_18,_2022 – Posted 5/13/22
All-Clear for Boil Water Advisory Issued for Demere Moss Condos on SSI on May 10, 2022
Effective immediately, as of 9:16 AM on Wednesday, May 11, 2022, all required microbiological testing of water samples from the area affected by the boil water advisory issued for Demere Moss Condos on SSI on Tuesday, May 10, 2022 have passed. Results have been verified by our state-licensed technician within a certified laboratory environment.
This notification is an ALL-CLEAR and water used for drinking will no longer need to be boiled.
Though the water from this system can now be...
Precautionary Boil Water Advisory – Demere Moss Condos on St Simons Island – Tuesday, May 10, 2022
DRINKING WATER WARNING
BOIL YOUR WATER FOR THREE MINUTES BEFORE USING
The St Simons Island water system lost pressure on the distribution network serving Demere Moss Condos off of Demere Road due to contractor damage to a main fitting. Once service has been restored, BGJWSC lab personnel will collect water samples for testing. This testing, which takes between 18 and 24 hours, should be completed the morning of Wednesday, May 11, 2022 at which time an all-clear message will be posted.
This...
Metering System Upgrade Project – Update 2
In early February 2021, the BGJWSC mobilized its meter installation contractor, M&E Construction, to install at or about 7,500 meters at various locations across Glynn County. Each of the 4 phases of this project will take 7 to 8 months to complete and will repeat again in similar batches until all 30,000 meters have been upgraded. This staggering of upgrades will help ensure that the batteries in the radio transmitters, which we expect to have a useful life of fifteen years, do not all...
Project Info – Mainland – Water Pollution Rehab-Academy
Project Number: #906
District and General Location: Academy Creek Water Pollution Control Plant on 2909 Newcastle Street.
Total Budget: $7.2M
Anticipated Construction Completion Date: Summer 2022
Details: The project has a variety of system improvement projects related to rehabilitation or replacement of unit processes and facilities at the plant to ensure continuous and reliable operations.
Purpose: The purpose of the project is to more effectively treat current flows and treat the...
Project Info – Mainland – Basin 4036 CIPP
Project Number: #2001
District and General Location: North Mainland District Pump Station 4036 Gravity Basin
Total Budget: $1M
Anticipated Construction Completion Date: Summer 2022
Details: The project consists of Cleaning, Closed-circuit television, and Cure-in-Place Pipe (CIPP) rehabilitation of the sewer mainline in the North Mainland District Pump Station 4036 Gravity Basin ranging from 15-inch to 30-inch in diameter
Purpose: The purpose of the CIPP process is to reduce and eliminate...
Project Info – Mainland – SPLOST 2016 Forcemain Reroute
Project Number: #702
District and General Location: North Mainland District along Harry Driggers Blvd, Canal Road, and Ogden Road
Total Budget: $4.7
Anticipated Construction Completion Date: Summer 2022
Details: The project consists of nearly 20,000 linear feet of 12- to 20-inch forcemain and 2,500 linear feet of 12 to 14-inch watermain will be installed via an open cut or trenchless directional drill method.
Purpose: The purpose of the project will reduce maintenance calls and...