Project Number:
District and General Location: Saint Simons Island District in the Westley Oak Neighborhood Subdivision
Total Budget: $450K
Anticipated Construction Completion Date: TBD
Details: The project consists of replacing the 2-inch galvanized watermain loop with 6-inch and 8-inch sections.
Purpose: The purpose of the project is to prioritize pipe repairs, rehabilitation, and replacements based on a risk-based, asset management strategy balancing the probability of a pipe failure...
Project Info – SSI – Ocean Boulevard Water Improvements
Project Number:
District and General Location: Saint Simons Island District along Ocean Boulevard
Total Budget: $1.75M
Anticipated Construction Completion Date: TBD
Details: The project consists of replacing the existing watermain from East Beach to the Village on Saint Simons Island.
Purpose: The purpose of the project is to prioritize pipe repairs, rehabilitation, and replacements based on a risk-based, asset management strategy balancing the probability of a pipe failure versus the...
Project Info – North Mainland WPCF Land Acquisition and Engineering
Project Number:
District and General Location: Located in the North Mainland District
Total Budget: $TBD
Anticipated Construction Completion Date: TBD
Details: The project consists of purchasing the property and plant engineering design to meet future infrastructure and system needs.
Purpose: The purpose of the project is to secure a future public wastewater treatment plant site to serve the North Mainland District residents on the public sewer system.
Have More Questions? Please Contact...
Project Info – South Mainland – Pump Station 3114 Forcemain Reroute
Project Number:
District and General Location: South Mainland District along South Port Parkway to the South Port Wastewater Treatment Plant
Total Budget: $400k
Anticipated Construction Completion Date: TBD
Details: The project consists of separate forcemain and reroutes to the head of the plant.
Purpose: The purpose of the project will reduce maintenance calls and disruptions. The reroute will also be shorter in length than the current alignment, which will result in energy savings and...
Project Info – SSI – Pump Station 2033 and 2034 Rehab
Project Number:
District and General Location: PS 2033 on 2913 Lawrence Road, Saint Simons Island PS 2034 on 130 Rice Mill Road, Saint Simons Island
Total Budget: $1.4M
Anticipated Construction Completion Date: TBD
Details: The project consists of the rehabilitation of Pump Station 2033 and 2034 due to the existing condition North end of Saint Simons Island.
Purpose: The purpose of the project is to ensure continuous delivery of wastewater to the Dunbar Treatment Plant. Improvements...
Project Info – SSI – Pump Station 2056 Pumps and Forcemain Improvements
Project Number:
District and General Location: Located in the Saint Simons Island District along Lawrence Road.
Total Budget: $700k
Anticipated Construction Completion Date: TBD
Details: The project consists of installing new pumps, discharge piping, and a parallel forcemain.
Purpose: The purpose of the project is to operate with better efficiency, reduce maintenance and provide up-to-date monitoring with enhanced technology. And for the new sewer main installation to reduce maintenance...
Project Info – Mall EST and Oglethorpe EST Rehab
Project Number:
District and General Location: Glynn Place Mall EST, North Mainland District Oglethorpe EST, Saint Simons Island District.
Total Budget: $1M
Anticipated Construction Completion Date: TBD
Details: The project consists of rehabilitation and painting for the Elevated Storage Tank (EST) at Glynn Place Mall EST and Oglethorpe EST.
Purpose: The purpose of the project is to provide reliable water supply and pressure for the surrounding community and fire suppression needs while...
Project Info – North Mainland – Pump Station 4105 Forcemain Reroute
Project Number:
District and General Location: Located in the North Mainland District along Cate Road and Crispen Boulevard toward Highway 341.
Total Budget: $1.25M
Anticipated Construction Completion Date: TBD
Details: The project consists of installing a new forcemain from Pump Station 4105 to Highway 341
Purpose: The purpose of the project will reduce maintenance calls and disruptions. The reroute will also be shorter in length than the current alignment, which will result in energy...
Project Info – Systemwide – Water Production SCADA
Project Number:
District and General Location: Systemwide upgrade for North Mainland, South Mainland, and Saint Simons Island District
Total Budget: $750k
Anticipated Construction Completion Date: TBD
Details: The project consists of converting the existing Water Production Supervisory Control and Data Acquisition (SCADA) to the new VTSCADA system. The existing control system receives input from several controls and instruments, many of which are reaching the end of their useful lives and...
Project Info – Academy Creek Ras Replacement
Project Number:
District and General Location: Academy Creek Water Pollution Control Plant on 2909 Newcastle Street.
Total Budget: $1.5M
Anticipated Construction Completion Date: TBD
Details: The project consists of replacing existing return activated sludge (RAS) pumps, piping, and electrical with chopper-style pumps due to the existing equipment systems reaching the end of their service life and needing to be replaced.
Purpose: The purpose of the project is to replace aging equipment to...