Project Info – SSI – Pump Station 2033 and 2034 Rehab

    • Project Number:
    • District and General Location: PS 2033 on 2913 Lawrence Road, Saint Simons Island PS 2034 on 130 Rice Mill Road, Saint Simons Island
    • Total Budget: $1.4M
    • Anticipated Construction Completion Date: TBD
    • Details: The project consists of the rehabilitation of Pump Station 2033 and 2034 due to the existing condition North end of Saint Simons Island.
    • Purpose: The purpose of the project is to ensure continuous delivery of wastewater to the Dunbar Treatment Plant.  Improvements include replacing pumps, equipment, electrical, and control systems.
    • Have More Questions? Please Contact W. Todd Kline, P.E., Director of Engineering by email here: tkline@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):